NEWS RELEASE TRANSMITTED BY CCNMatthews

FOR:  HIGH RIVER GOLD MINES LTD.

TSX SYMBOL:  HRG

JUNE 14, 2004 - 16:40 ET

High River Gold Releases Bankable Feasibility Study
Results for the Taparko-Bouroum Gold Project

TORONTO, ONTARIO--(CCNMatthews - Jun 14, 2004) - (TSX:HRG) - High 
River Gold Mines Ltd. ("High River") is pleased to release the 
results of the recently completed bankable feasibility study for 
the combined Taparko-Bouroum Gold Project, located in Burkina 
Faso, West Africa. High River owns an 80% interest in the 1,204 
square kilometre Taparko property with the Government of Burkina 
Faso holding the remaining 20% interest (5% of which is 
participating). The Bouroum property is held by AXMIN Limited; 
negotiations are currently underway regarding the possible 
acquisition by High River of AXMIN's interest in Bouroum. There 
are a number of deposits on both properties of which six will be 
exploited, three located on each of Taparko and Bouroum. 

During 2003, High River initiated a feasibility study utilizing a 
combination of international and in-house engineering expertise 
to meet international standards as well as Burkina Faso 
regulatory and permitting requirements. Financial analysis 
highlights from the Feasibility Study are presented in Table 1, 
results including IRR and NPV are presented in Table 2 and 
operating highlights underlying the study are presented in Table 
3. Talks are well advanced with financial institutions to secure 
debt funding for the project. 


/T/

Table 1. Financial Analysis Highlights.

---------------------------------------------------------------------
Average Cash Cost per ounce of gold (US$)                        $204

Government Royalty per ounce of gold (3%)                      $10.50

Average Operating Cost per tonne of ore (US$)                  $17.24

Capital Expenditures (US$)(1)                           $51.9 million

Sustaining Capital (US$)                                $ 4.0 million
---------------------------------------------------------------------

(1) Includes 10% Contingency
    The project is Value Added Tax (VAT) Exempt during the
    development and construction phase.

Table 2. Financial Analysis Results (IRR and NPV)

---------------------------------------------------------------------
                                                Gold Price
                                   ----------------------------------
                                   $350/oz       $400/oz      $450/oz
---------------------------------------------------------------------
Internal Rate of Return (IRR)        15.5%         24.6%        32.9%

Net Present Value (US $): (0%)       $38.0         $65.8        $93.9
                          (5%)        20.4          41.3         62.3
                         (10%)         8.6          24.7         40.8
---------------------------------------------------------------------

Table 3. Operating Highlights.

---------------------------------------------------------------------

Measured and Indicated Resources(1)
                          - Taparko  10.5 million tonnes @ 2.7 g Au/t
                          - Bouroum   2.2    "       "   @ 3.1 g Au/t

Ore Reserves(1)
                          - Taparko   6.8    "       "   @ 2.8 g Au/t
                          - Bouroum      861,000 tonnes @ 3.97 g Au/t

Mine Life                                                   7.6 years
Average O/P Stripping Ratio (W/O)
                          - Taparko                          4.36 : 1
                          - Bouroum                          7.21 : 1

Processing Plant Throughput
 (tonnes/year)                                            1.0 million

Overall Gold Recovery
 (Taparko/Bouroum)
                          - Oxide                        97.5 / 97.4%
                          - Transition                   94.1 / 90.0%
                          - Sulphide                     90.5 / 84.3%

Total Gold Produced                                       684,700 oz.
---------------------------------------------------------------------

(1) Mineral resource and reserve estimates are in accordance with
    National Instrument 43-101.

/T/

Project Schedule 

The current project schedule is presented in Figure 1. Commercial 
production is expected to be reached during the fourth quarter of 
2005, after a one and a half year construction period. This is 
based on all permits and debt financing being in place by the end 
of the second quarter of 2004. 


/T/

Figure 1. Project Schedule.

---------------------------------------------------------------------
Component                            2004                  2005
                              ---------------------------------------
                              Q1   Q2   Q3   Q4     Q1   Q2   Q3   Q4
---------------------------------------------------------------------
Detailed Engineering                     x    x
---------------------------------------------------------------------
Procurement                              x    x      x
---------------------------------------------------------------------
Site Preparation                              x
---------------------------------------------------------------------
Roads                                         x      x    x    x
---------------------------------------------------------------------
Mine Development                              x      x
---------------------------------------------------------------------
Processing Plant Construction                 x      x    x    x
---------------------------------------------------------------------
Infrastructure Facilities                     x      x    x    x
---------------------------------------------------------------------
Tailings Storage Construction                 x      x    x
---------------------------------------------------------------------
Electrical/Power                              x      x    x    x
---------------------------------------------------------------------
Commissioning                                                  x
---------------------------------------------------------------------
Commercial Production                                               x
---------------------------------------------------------------------

/T/

Overview 

The Bankable Feasibility study for the 1.0 million tonnes per 
year Taparko-Boroum Project was prepared by a number of 
independent consulting organizations and High River Gold 
personnel. The Qualified Person in charge of the overall 
execution of the feasibility study is Daniel G. Vanin, P. Eng., 
High River's Chief Operating Officer. The geology and mineral 
resource estimate, open pit optimization, mineral reserves and 
mining sections were provided by SRK (Canada) Inc., Toronto, 
Canada. Geotechnical evaluations were performed by Golder 
Associates, Canada. Metallurgical testwork was performed by 
Lakefield Research, South Africa and SAG mill sizing work was 
performed by Minnovex, Toronto, Canada. Processing plant and 
infrastructure requirements assessments were performed by 
Metallurgical Design and Management, South Africa, with tailings 
storage and water management portions provided by ECMP, South 
Africa. Roche Limited, Consulting Group, Canada prepared the 
environmental sections. Remaining portions were prepared by High 
River Gold. 

The Taparko-Bouroum Mine is planned to be an open pit operation 
using excavators, a loader and trucks. The processing plant will 
be comprised of crushing, a semi-autogenous/ball mills 
combination for grinding, gravity concentration and 
carbon-in-leach (CIL) gold extraction. Gold is recovered from 
carbon by pressure stripping and electrowinning, with gold 
smelted into dore bars on site. 

Mineral Resource/Reserve Estimation 

During 2003, SRK conducted an audit of the resources in the 
Taparko-Bouroum Deposits. 3-D wireframe models were created from 
a GEMCOM database which for the Taparko Zones contains in excess 
of 680 core and reverse circulation drill holes and 107 surface 
trenches. The current database for the Bouroum Property consists 
of 295 core and reverse circulation holes. Grade capping for the 
deposits were determined and varied between 15 grams Au per tonne 
and 40 grams Au per tonne. A cut-off grade of 1 gram Au per tonne 
was used to define the mineralized envelope and preserves 
continuity while ensuring all potentially economic mineralization 
is included in the wireframe models. 

The mineral resources have been calculated consistent with "CIM 
Standards on Mineral Resources and Reserves - Definitions and 
Guidelines" the report of the Standing Committee on Reserve 
Definitions dated October, 2000. At a 1 gram Au per tonne cut-off 
grade, the Indicated Mineral Resources are estimated at 10.5 
million tonnes at an average grade of 2.7 grams Au per tonne for 
Taparko and 2.2 million tonnes at an average grade of 3.1 grams 
Au per tonne for Bouroum. 

Mineral Reserves 

The mineral reserves were developed by SRK using Whittle 4X open 
pit optimization software, with a mining rate of 1.0 million 
tonnes of ore per year. The optimized pit shell was then adjusted 
to include haul roads and minimum mining widths for equipment. 

The mineral reserves at $US350 per ounce of gold and including 10 
percent dilution are: 


/T/

Taparko  6.75 million tonnes  2.78 g Au/t   604,270 ounces
                                            contained gold
Bouroum  861,000 tonnes       3.97 g Au/t   109,993 ounces
                                            contained gold

/T/

Mining 

Mining operations will be carried out in six open pit operations, 
three at Taparko and three at Bouroum. Ore and waste will be 
mined using primarily two excavators, one loader as required and 
ten haul trucks, all diesel operated. The excavator will be 
equipped with 5 cubic metre buckets, the loader with a 6.5 cubic 
metre bucket and the trucks will be 54 tonnes capacity. All ore 
and waste (except the Saprolite waste) will be drilled and 
blasted. Ore will be hauled by truck to the processing plant. Ore 
from Bouroum will be trucked approximately 45 kilometres to the 
Taparko processing plant for treatment. Waste rock will be placed 
in waste stockpiles located adjacent to open pit operations. The 
mine production schedule is based on mining 1.0 million tonnes of 
ore per year. The resulting mine life is approximately 7.6 years. 
The Bouroum operations are mined over 3 years with a total 
average stripping ratio of 7.21. The Taparko operations extend 
over the total mine life with an average stripping ratio of 4.36. 


Metallurgy 

The Taparko-Bouroum deposits are a combination of lower 
grade/medium volume (Taparko) orebodies and higher grade/low 
volume (Bouroum) orebodies. The ore exhibits no refractory 
characteristics. Ores consist of oxide, transition and sulphide 
mineralization. 

Extensive past testwork had been performed on Bouroum ores. The 
feasibility study testwork focused on Taparko material with only 
variability work performed on the smaller Taparko deposits and 
also on Bouroum ore (because of past testwork). Metallurgical 
testing has shown the ore to be amenable to cyanide leaching and 
concentrating of free gold by gravity separation. The feasibility 
testwork was performed by Lakefield Research, South Africa. 
Overall processing plant gold recoveries for oxide, transition 
and sulphide materials are expected to be 97.5 / 97.4%, 94.1 / 
90.0% and 90.5 / 84.3% for Taparko and Bouroum ores respectively. 


Processing 

The processing plant will crush the ore and grinding will utilize 
a semi-autogenous mill followed by secondary ball mill grinding. 
A gravity recovery circuit, for recovery of free gold in the 
grinding section, will produce a gravity concentrate. 

Subsequent gold extraction will be by carbon-in-leach using 
cyanide, pressure stripping of gold from the carbon, 
electrowinning of gold from solution and refining to produce gold 
dore bars. 

The plant and infrastructures have been designed to allow for an 
expansion. 

Tailings and Water Management 

Tailings will be placed as a slurry and solids settled out, in an 
impoundment area lined with an HDPE geomembrane. The facility 
will include a perimeter dam. Water will flow to a return water 
reservoir where the water will be pumped back to the processing 
plant for reuse. 

Process and potable water for the project will be provided from a 
new reservoir on the Taparko property fed from the existing 
Yalogo Reservoir, nine kilometres from the mine property. Potable 
water will be provided from wells drilled on the Taparko and 
Bouroum Properties. 

Infrastructure and Services 

The mine is located 200 kilometres north east of the capital city 
of Ougadougou, via a 100 kilometre paved road and 100 kilometre 
gravel road. Both are serviceable for the project. Freight 
destined for the mine will arrive at the port of Tema in Ghana 
and be trucked from there. 

Electrical power will be provided by on site diesel generators 
with a total operating capacity of 8.4 mW. Other services 
facilities to be constructed on site include a main entrance 
security building, mine maintenance shop, warehouse, 
administration building, security and changehouse building for 
the processing plant, fuel and lubricants storage and 
distribution, explosives magazines, water collection and 
treatment networks, sanitary landfill and sewage treatment 
facilities. A camp to accommodate and provide meals for the 
employees will be built and include kitchen, catering and 
recreational facilities 

Environmental Management 

An Environmental Impact Assessment study was carried out by Roche 
Limited and local Burkina Faso consultants. All sources of impact 
were assessed and impacts minimized in the design and operations 
phase. Off-site and on-site monitoring will be undertaken during 
the life of the mine and audits of performance provided by 
external organizations. 

Capital Expenditure Estimates 

The total capital expenditure required for the project is 
forecast at US $51.9 million. The breakdown of capital 
expenditures, with a contingency of 10% included, is shown in 
Table 4. 


/T/

Table 4. Capital Expenditures

---------------------------------------------------------------------
Component                                        Cost (US $ millions)
---------------------------------------------------------------------
---------------------------------------------------------------------
Infrastructure                                                    3.6
Open Pit Equipment and Facilities                                 8.8
Processing Plant                                                 11.9
---------------------------------------------------------------------
Tailings & Water Management                                       6.7
Power & Communications                                            5.5
General & Administration                                          2.9
Construction & Shipping                                          12.5
---------------------------------------------------------------------
---------------------------------------------------------------------

TOTAL EXPENDITURES                                           US $51.9

---------------------------------------------------------------------

/T/

Operating Cost Estimates 

Total average cash costs, including royalty, for the life of the 
mine are US $214 per ounce of gold. The average operating cost 
per tonne of ore is US $17.24. Unit operating costs are shown in 
Table 5. 


/T/

Table 5. Unit Operating Costs

---------------------------------------------------------------------
Component                                               Cost (US $/t)
---------------------------------------------------------------------
---------------------------------------------------------------------
Mining                                                           6.06
Processing                                                       8.21
General & Administration                                         2.53
Other (Fees,etc.)                                                0.44
---------------------------------------------------------------------
---------------------------------------------------------------------

TOTAL OPERATING COST per tonne                              US $17.24

---------------------------------------------------------------------

/T/

Expansion Strategy 

High River has designed the Taparko facility with a longer term 
operation in mind with the belief there is excellent potential to 
define additional satellite deposits. High River controls, 
directly or indirectly through an agreement with Jilbey Gold 
Exploration Ltd., in excess of 3500 square kilometres of 
prospective property within trucking distance of the planned 
Taparko mill. The agreement with Jilbey provides High River with 
back-in and operatorship rights on discoveries within trucking 
distance of the mill and a right of first refusal on discoveries 
outside trucking distance. 

A sensitivity study, using a gold price of US $400 per ounce, 
more than doubles the gold resource to 1.3 million ounces for the 
three Taparko pits. This significantly increased resource at US 
$400 gold demonstrates the potential for expanded production 
and/or an extended mine life at Taparko. 

Forward-Looking Statements 

This report contains forward-looking statements based on current 
expectations. These forward-looking statements entail various 
risks and uncertainties that could cause actual results to differ 
materially from those reflected. Risk and uncertainties about the 
Company's business are more fully discussed in the Management's 
Discussion and Analysis published in the Company's Annual Report 
and Annual Information Form. 

-30-
FOR FURTHER INFORMATION PLEASE CONTACT:
High River Gold Mines Ltd.
David Mosher
President and CEO
(416) 947-1440
(416) 360-0010 (FAX)

or

High River Gold Mines Ltd.
Don Whalen
Chairman
(416) 947-1440
(416) 360-0010 (FAX)
highrivergold@hrg.ca
www.hrg.ca
 
 

You can return to the Top of this page